Petro Jayna, the Chinese company, started to implement a project to extend the gas pipeline supplier to Al-Kehala gas generation plant.
Director of Maysan Oil Company Ali Maarej said that "Petro Jayna began to extend the equipped gas tube to Al-Kehala power plant from Halfaya oil field with a length of 21 kilometers."
He added that "the cost of the project amounted to $ 36 million," adding that" additional units will be set up near the RTS to receive special gas and purified of impurities as well as horizontal insulator and three heaters."
The productive capacity of the gas station of Alekhala is 180 MW and until recently, it needs gas pipeline to ensure the sustainability of operation. "