| | |  |  | | Reconstruction of service departments in Falluja started
Baghdad Ministry of municipality and general labor has carried out a number of service projects in the city of Falluja with a cost $ 800,000 allocated from DAI which is a donation from US humanitarian organizations. A source at the ministry said that the sum has been allocated for rehabilitating eight pumping stations , achieving constructional works for each department besides managing, , furnishing ,and supplying them with electricity generators hopeful to be fulfilled by end coming month. He added four sinking pumps with a capacity 500 cubic meters an hour specialized for Jihad/10 pumping station which were excluded from rehabilitation works due to volume of damage inflicted on them.
| |
| |
| |